Fedder's Alley Playground in Washington Park, Michigan City: What's Planned

October 29, 2026

"Our playground was thoughtfully designed with one core principle in mind: everyone, regardless of ability, should have the opportunity to play." Parks & Recreation Superintendent Shannon Eason said that in a City of Michigan City release the day after the Common Council voted to fund the last piece of the project. Seven months later, the project is the reason a familiar stretch of Washington Park is closed to cars.

In October, Michigan City Parks & Recreation announced that construction had begun on the Fedder's Alley All-Inclusive Playground & Fitness Park. Crews are doing earthwork, grading the site and getting it ready for asphalt. With construction vehicles going in and out, the department closed Fedder's Alley to drive-through traffic for the rest of the season. You can still walk through to the beach paths.

How the park was put together explains a lot about it. The $5 million came in pieces from about a dozen sources over two years. One of the first big grants set money aside to maintain the park before anyone broke ground. That kind of fund is new for the city's parks department.

What the Crews Are Grading For

The parks department describes the playground as a design where meeting ADA standards was "the starting point, not the finish line." The department says every piece was chosen "so more people can play together," and for most of them it names who they serve:

Feature Who the parks department says it serves
Sensory pods Kids who get overstimulated and need a quiet place to reset
Metal slide Kids with cochlear implants who can't handle a static charge
Musical components Kids who are understimulated and visitors who are hearing impaired
Weighted components Older community members who still enjoy a playground

The list also includes adaptive swings and zip lines, plus Braille and sign language on the name plates.

There is more to the project than the play equipment. Plans include a walking trail through Fedder's Alley, an outdoor workout pad, public art, and a new restroom building with family bathrooms and adult changing stations. The city calls it a destination playground, "the first of its kind in Northwest Indiana." The design team includes JPR, which reports doing the topographic and boundary surveys and designing the restroom building.

Washington Park's official map shows Fedder's Alley inside the park, along the lakefront. Mayor Angie Nelson Deuitch called the area a place that has "long been a gathering place for our community." The new park goes on land people already use, which explains the walk-through access during construction.

A $5 Million Park, Paid For in Pieces

The city launched a $2 million capital campaign in September 2024 for a project expected to cost about $5 million. The rest came from many directions. Here are the commitments the city and the parks department have announced:

Source Amount Where it was announced
Michigan City Common Council $1.5 million Parks Department, 2025
Federal funding secured by U.S. Rep. Frank Mrvan $1 million Parks Department, 2025
Health Foundation of La Porte $750,000 Parks Department, 2025
Michigan City Redevelopment Commission $500,000 Parks Department, 2025
Google $400,000 City release, May 2026
1st Source Bank $75,000 Parks Q2 2026 report
Duneland Health Council $50,000 Parks Department, 2025
United Way of La Porte County $25,000 City release, March 2026
Riverboat Fund appropriation Up to $600,000, as "last in" money City release, March 2026

The March 2026 council meeting was when the project went from "almost" to "funded." When it opened, the city had about $3.9 million lined up. The council unanimously approved $600,000 from the Riverboat Fund. The city described that as "last in" money that might never be spent if more private funding came through. According to the city, the vote let the project keep grant money that was set to expire April 7. Two pledges came during public comment at that meeting. Kris Pate, president and CEO of United Way of La Porte County, offered $25,000. Then Councilwoman Nancy Moldenhauer said that she and her spouse were the previously unnamed "individual donor."

Google closed the gap. At a Common Council meeting in May 2026, the company announced it would give the final $400,000, and the city said that finished fundraising for the $5 million project. The city credits a long list of partners. Besides the funders above, it names the Economic Development Corporation and the Michigan City Human Rights Commission. The pieces in the table don't add up to an exact total, partly because the Riverboat money was conditional. The city's own position is that the project is fully funded.

The Line Item Meant to Outlast the Ribbon Cutting

Splitting the funding this way changes what the park will look like years after it opens. When the Health Foundation of La Porte gave its $750,000 grant, it put conditions on it. Of that money, $500,000 goes to construction. The other $250,000 starts a long-term maintenance fund for the park. The parks department calls it the first fund of its kind for Michigan City Parks & Recreation.

Sensory pods, adaptive swings and a static-free metal slide are specialized equipment. A playground built for every ability works only while that equipment is in good repair. The foundation's grant set aside upkeep money before the first load of asphalt base arrived, so maintenance isn't left to compete with every other parks need once the opening is over.

Fundraising also keeps going in a smaller way. The parks department says several structures are still open for sponsorship. Donations go through the project fund at the Unity Foundation of La Porte County. The department has also posted a virtual tour on YouTube for anyone who wants to see the finished design before the fencing comes down.

Two Years From Campaign Launch to Grading

If the start date surprises you, it's because the schedule moved several times. A GreatNews.Life report on the 2024 campaign launch said a ribbon cutting was expected the following fall. In early 2025, the parks department expected groundbreaking that year. In March 2026, the city said construction would begin in 2026. The Park Board's June 3, 2026 agenda included "Open Bids for Fedder's Alley Playground." Work started in October.

The order of events is clear from the table. Funding wasn't complete until May 2026. Bids opened in June, and crews arrived in the fall. The parks department's October update doesn't give an opening date, so plan on the drive-through closure lasting through the off-season. The department said it would last "for the rest of the season."

Washington Park Between Now and Then

Construction takes up one section of the park. The rest of Washington Park keeps its usual off-season schedule, and some of it is busy:

  • Fedder's Alley on foot. The drive-through is closed, but you can still walk through to the beach paths.
  • Washington Park Zoo. According to the zoo's posted hours, it's open Saturdays and Sundays only from Nov. 1 through Dec. 5, 10 a.m. to 4 p.m., with last entry at 3 p.m. It then closes for the season from Dec. 6 until April 1, 2027.
  • Festival of Lights. Michigan City's free Festival of Lights runs Dec. 5, 2026 through Jan. 10, 2027, with light displays in Washington Park. It opens with a parade on Franklin Street at 5 p.m. on Dec. 5. Michigan City Special Events hosts it with Parks & Recreation.
  • The next parks plan. Parks & Recreation is collecting input for its 2027–2030 master plan. The survey closed Oct. 16, and the department listed the Nov. 4 Park Board meeting as another chance for public comment.

The master plan and Fedder's Alley are connected. Fedder's Alley shows what this city can build when a council vote, a federal appropriation, local foundations and a corporate gift all go to one site. The 2027–2030 plan will help decide which site comes next.

I grew up in Michigan City, and I've watched Washington Park's lakefront from the same shoreline where I work every day. If you want to talk about what the lakefront's next few years mean for your plans, whether you're staying put, buying near the park or getting ready to sell, Jordan Gallas is glad to help. Let's Connect.